How developers are reshaping Sydney’s Eastern Suburbs
An investigation by Alan Weiss | Housing Delivery Authority, land values and the economics of new apartments
A panel of three, and a new door for developers
After more than 35 years in Sydney real estate, I have seen planning changes transform the value of land. The Housing Delivery Authority (HDA), established in December 2024, changes the route by which major housing proposals can reach state assessment. It does not itself grant development consent. My original investigation recorded more than 300 declarations by December 2025 and a potential pipeline exceeding 102,000 homes. These are historical pipeline figures, not completed dwellings or a current November 2026 count.
The NSW Housing Accord target is 377,000 homes by June 2029. The HDA and Low and Mid-Rise (LMR) reforms are separate mechanisms for increasing delivery. In the Bondi Junction property market, transport access and established amenities make the implications particularly important.
Three planning layers
LMR standards apply to eligible mapped land, not every parcel within a simple radius. Infill affordable housing incentives may allow additional height and floor space where statutory conditions are met. HDA recommendation and SSD declaration can enable assessment of larger proposals, including concurrent rezoning where appropriate. None guarantees a particular height, yield or approval. Check zoning, exclusions, heritage, hazards and the applicable instrument for each site.
Seven stages from proposal to determination
- Expression of interest: demonstrate scale, location, housing delivery, tenure and feasibility against current criteria.
- HDA evaluation: recommendation, possible concurrent rezoning, alternative pathway or non-recommendation.
- Ministerial declaration: SSD status is not development consent; resolve overlapping applications as required.
- SEARs: environmental assessment requirements define the studies needed.
- DA and EIS: prepare and lodge the application within applicable deadlines.
- Assessment and exhibition: department, agencies, council and community provide input.
- Determination: the applicable state consent authority decides; conditions and subsequent approvals still matter.
The original investigation cited indicative $60m metropolitan and $30m regional thresholds, a nine-month lodgement period and a 275-day assessment target. These are historical policy settings, not guaranteed current eligibility or timelines. A project can take substantially longer from declaration to construction and settlement.
What happens to council power?
For state-determined SSD, council is generally not the consent authority. It can still provide submissions, local infrastructure advice and input on assessment requirements. LEPs remain legally relevant subject to SSD provisions and any rezoning; DCPs generally do not apply to SSD. Ordinary local DAs remain subject to applicable statutory controls, and LMR non-refusal standards do not remove all assessment discretion. The consent authority and IPC referral rules depend on the specific declaration and statutory framework.
Eastern Suburbs case studies: the historical pipeline
The following tables reproduce the project details recorded in my April 2026 investigation. They are historical snapshots, not verified current statuses. A declaration, SEARs request or EIS preparation is not an approval. Mosman is included as a comparison outside the Eastern Suburbs.
| Site | Proponent | Scheme | Declared SSD | Status |
| 16–24 Belmore Road, Randwick | Randwick town centre site | 15-storey shop-top housing, ~104 apts, 15% affordable housing for 15 yrs | 15 July 2025 | Prepare EIS |
| 123–139 Alison Road & 11 Elizabeth Lane, Randwick | — | 115 dwellings with concurrent rezoning | 15 July 2025 | Prepare EIS |
| 135–155 New South Head Road & 529–539 Glenmore Road, Edgecliff | — | 109 dwellings with concurrent rezoning; earlier tower sketch 12–27 storeys | 8 August 2025 | Prepare EIS |
| 669–683 Old South Head Road, Vaucluse | OSHR at Vaucluse Holdings (Meissen Properties / Aquavenus); Blare Management | 82 senior-living units + 21 affordable dwellings in three buildings 6.5, 7.5 & 9.5 storeys; $155m est. | 29 August 2025 | SEARs requested |
| 77–103 Anzac Parade & 59A–71 Boronia Street, Kensington | Architectus (planner); previous Anson Group scheme nearby | 357 apartments, 24 storeys, 15% affordable; supermarket + through-site link | 10 October 2025 | Prepare EIS |
| 122–128 Hewlett Street, Bronte | Fortis | 100–120 dwellings, part 4-storey + part 9-storey, 5% affordable | 9 December 2025 | Newly declared |
| 35–45 Awaba Street, Mosman | Heworth Holdings Group | 9-storey residential, 100 dwellings, 4% affordable housing in perpetuity | 9 December 2025 | Newly declared |
Vaucluse and Kensington: the scale of the uplift
At 669–683 Old South Head Road, the original investigation compared an earlier 31-dwelling seniors scheme with a proposed 103-dwelling scheme including 21 affordable dwellings. At Anzac Parade, Kensington, it compared 197 apartments with a proposed 357. These are scheme comparisons, not confirmation that the larger schemes have been approved or built.
Double Bay: the difference between an asking price and a sale
11–13 Ocean Avenue was marketed in early 2026 with expectations above $80 million, according to the original investigation. The 2,694 m² site and 12 existing apartments illustrate how redevelopment expectations can enter vendor pricing. An asking price is not a settled transaction or independent valuation. The Rose Bay development analysis explores similar pressures on premium land.
Proposals not recommended in the historical snapshot
Non-recommendation for the HDA route is not necessarily refusal of a development application. Some proposals were directed toward existing local applications or precinct planning.
| Site | Proposal | Proponent | Core reason HDA declined |
| 20 Kiaora Road, Double Bay (Woollahra) | 105 apts, up to 12 storeys, 10% affordable | Planning&Co | Wait for Woollahra station SLR |
| 73–85A New South Head Road, Edgecliff (Woollahra) | 126 apts, 21 storeys, 15% affordable | GSA Planning | Wait for Edgecliff-Woollahra SLR |
| 109, 113 & 115 New South Head Road, Edgecliff (Woollahra) | 107 apts, 25 storeys, 15% affordable | Avenor | Wait for Edgecliff-Woollahra SLR |
| 3 Fullerton Street, Woollahra | 101 apts, 22 storeys, 5% affordable | Fullerton Street Developments | Wait for Edgecliff-Woollahra SLR |
| 1 & 3–5 The Avenue and 439–445 Old South Head Road, Rose Bay (Waverley) | Mixed-use, residential units including affordable (DA-245/2024 on foot) | Orosi | Told to progress the existing DA through council instead |
| 1406–1408 Anzac Parade, Little Bay (Randwick) | 2,600-dwelling concept, Stage 1 of 400 apts, 2–27 storeys, 5% in-perpetuity affordable | Karimbla Constructions (Meriton) | Precinct planning required first; transport & hazard concerns |
| 11–27 Jennifer Street, Little Bay (Randwick) | 150 apts, 6–7 storeys, 20% affordable | Urban Property Group | Progress the existing DA consent instead |
| 5–9 Eden Street & 39 Burrows Street, Arncliffe (Bayside) | 140 apts, 22-storey tower, 10% affordable for 15 yrs | AMA Corp (NSW) | Intrudes into Sydney Airport Obstacle Limitation Surface |
Bondi Road and Maroubra: two different routes
The original investigation records a court-approved 46-apartment scheme at 7–19 Bondi Road and a larger 150-dwelling proposal at 7–21 Bondi Road. The sites overlap but are not identical. In Maroubra, it records a refused 56-unit scheme at 138 Maroubra Road and a separate 130-unit proposal at 86–94 Maroubra Road and 46 Hannan Street. These examples illustrate different pathways, not proof that state assessment guarantees success.
What does the development opportunity actually cost?
Planning fees, design, consultants, environmental studies, legal work, affordable housing, infrastructure contributions, finance and construction all reduce the residual available for land. My original investigation estimated $500,000–$1.5 million in preliminary costs for some major schemes. This is a scenario range, not a fee quote. Obtain current official fee schedules and professional estimates.
Local DA applicants may have merits appeal rights under the EP&A Act. SSD appeal rights depend on the determination and statutory exclusions; judicial review addresses legality rather than planning merits. Do not assume every SSD decision excludes merits appeals or that every challenge has the same deadline. Seek planning legal advice promptly.
Interactive development feasibility model
Base residual
Stressed residual
Illustrative nominal model. Non-land costs must include all construction, finance, fees, selling costs and contingencies on a consistent tax basis. Affordable housing proceeds are assumed net receipts, not a statutory valuation. Negative residuals indicate infeasibility and are shown numerically.
A housing shortage can coexist with luxury apartment oversupply
In Double Bay, Rose Bay, Edgecliff and Woollahra, multiple developments may target the same downsizer. The proposed Woollahra–Edgecliff precinct changes could add further competition over time, but draft controls and delivery schedules must be checked before assuming any dwelling count. A citywide shortage does not guarantee demand for $4–8 million apartments. Buyers can delay, compare incentives or retain their family homes. Developers may stage releases, redesign or defer construction.
Interactive apartment absorption model
Constant net sales and releases; no cancellations, staging changes or demand shifts. This is a scenario, not a local sales forecast.
For existing homeowners, development potential may increase interest from developers, while nearby construction, privacy loss, traffic and competing apartments can affect ordinary residential buyers. Before selling, compare actual settled sales and obtain site-specific planning advice. My personal property selling service focuses on the achievable market, not theoretical yield. For purchasers, a property buying strategy should include strata records, future supply and settlement risk.
My verdict
The HDA is a deliberate state planning pathway, not a guarantee of profit. The next cycle will reward developers who buy land at a price supported by realistic sales, and homeowners who understand their actual alternatives. In a softer market, waiting for a theoretical rezoning premium can carry a real cost. Follow my Sydney property market research for further analysis.
Source basis: supplied investigation, material accessed through April 2026, including NSW DPHI HDA records of briefing, NSW Planning Portal, Housing SEPP, Land and Environment Court and cited industry reporting. Historical project details have not been independently refreshed. General information only; obtain current planning, legal and financial advice.