That article listed ten developments coming to the Eastern Suburbs and described all of them as exciting. Every one was real and every description was accurate. What it did not do, and what any piece about infrastructure has to do if it is going to be useful, is tell you how likely each one was to happen and when. Three years later one of them is open and does not yet do what it promised, one is in the Land and Environment Court, several are approved and not started, and a few I simply cannot confirm either way. If you are buying near a project, that distinction is the only thing that matters. Where I have been able to confirm the current status from a primary source, I have. Where I have not, I say so rather than repeating the 2023 description as though it were current. That honesty is the point of the exercise. 9,400 homes, 34 storeys and a new station: the Edgecliff–Woollahra rezoning. Precinct by precinct across the East: the LMR reforms. I described it in one breezy sentence as ready to take us on a thrilling ride, with a note that it had seen some debate. Here is what “some debate” turned into. Identified as a high-priority missing link in the Eastern Harbour City strategic cycleway corridor between Bondi Junction and the CBD. The Bondi Junction cycleway opened in March 2023 and the Centennial Park cycleway back in 2014. Scheduled to start in October 2023, delayed to March 2024, with completion expected by the end of 2024. The Oxford Street West and Liverpool Street cycleway, connecting the CBD to Taylor Square, delivered by the City of Sydney. More than 2,000 riders a day already used the corridor, which was a recognised crash hot spot. Lodged by the local member and signed by more than 500 people, calling for the 1.8 kilometre eastern section from Taylor Square to Centennial Park to be dropped. The Transport Minister formally rejected it. Two Paddington residents launched proceedings against the state government and the City of Sydney, alleging the project breaches human rights laws by discriminating against elderly people and those with a disability. Woollahra Council does not support the eastern section. The Moore Park Road pop-up cycleway, meant to be removed by 31 May 2026 or when Oxford Street East became operational, has been extended to 31 December 2026. Five years after the proposal, the section that would actually connect the Eastern Suburbs to the city is not under construction. Sources: Transport for NSW; City of Sydney; Bicycle NSW; the Paddington Society; media reporting. Positions and timelines in a contested project change frequently. This is the one I would most want a buyer to understand, because it is the pattern that catches people out. The infrastructure was delivered on schedule and to specification. The service it was built for is a separate stage that has not started. The $49.3 million project replaced wharves at La Perouse and Kurnell as part of the Kamay Botany Bay National Park master plan, and opened for public use on 27 February 2025. They are roughly 230 metres at La Perouse and 250 at Kurnell, built for drop-off and pick-up berthing, fishing and gathering, with a seagrass restoration zone where anchoring is not permitted. Transport for NSW describes stage one as wharf operation and stage two as a potential future ferry connection, with conditions of approval to be met at each stage. As at the middle of 2026 the project page still refers to future ferry connections. A ferry ran between Kurnell and La Perouse from the 1890s until storms destroyed the wharves in 1974. If you bought in La Perouse or Phillip Bay on the strength of a twenty-minute ferry link replacing a ninety-minute drive, you own a very good wharf. The link itself requires an operator, a business case and a second set of conditions. None of that was secret. It was in the project documents the whole time, and none of it was in my article. This is the tool I wish I had included in 2023. When an agent or a council or a developer tells you something is coming, the only useful question is which stage it is at, because each stage carries a very different probability and a very different timeframe. Pick one.
Three years is long enough for the pipeline to turn over. The projects most likely to affect Eastern Suburbs values today were not in that article because most of them did not exist yet. Up to 9,400 homes across 168 hectares, heights to 34 storeys at Edgecliff and 32 at the proposed Woollahra station. Exhibition closed 30 October 2026, outcome expected 2027. Far larger in consequence than anything on the 2023 list. Construction slated to begin in 2027 for a 2029 opening, about eight minutes to the CBD. Sydney’s first new heavy rail station in more than a decade, and the single most durable change in this whole pipeline. A state significant mixed-use development with infill affordable housing, determined on 24 September 2026 despite extensive community objection, with roughly 83 excavated parking spaces. A second proposal at Oxford and Verona Street is in assessment. A five to six storey shop-top housing proposal with 13 apartments refused on 10 September 2026 over amenity, flooding, traffic, setbacks and desired future character. Coogee remains one of the harder approval environments in the East. Contract, planning certificate, title and strata, in the order they matter: due diligence in NSW. Clearance at 52.8% and values 10.1% below the February peak: downturns compared. Reading it back is uncomfortable. Jaw-dropping, hold onto your hats, exciting times ahead my friends. Every project in it was real and correctly described, and the piece was still close to useless, because enthusiasm is not information. A person reading that article was probably trying to work out whether to pay more for a flat near one of those projects. Nothing in it helped them do that. The last four paragraphs were generic agent copy about being your guiding light, which is the part I would delete first. What I would write instead is on this page. Of the ten, the wharves at Kamay are open and the ferry they were built for has not started. The Oxford Street cycleway took 1,360 days to deliver its first half and the second half is being litigated. The Coogee Bay Hotel was approved three years ago under a deferred commencement consent and the architects still list it as ongoing. Several of the rest I genuinely cannot confirm, and I would rather tell you that than repeat a 2023 sentence with a 2026 date on it. The practical rule I have arrived at is simple and it has cost clients real money when they ignored it. Do not pay today for infrastructure that has not been built. If a station, a cycleway, a ferry or a shopping centre upgrade is in the price, you are funding someone else’s optionality. Buy the property for what it is now, on the street as it is now, and treat the project as upside you did not pay for. In the Eastern Suburbs over three decades that approach has never once left me explaining to a client why the thing on the brochure is still a vacant lot. Someone on your side of the table who will check the stage before you bid: my buying service. How to price in genuine upside without promising what has not been approved: my selling service. Which approvals exist, which conditions are outstanding, who controls the next gate, and whether any of it should be in what you pay. Thirty-five years of watching Eastern Suburbs projects arrive late or not at all. Several projects from the original article could not be confirmed from a primary source and are marked unconfirmed rather than restated; their 2023 descriptions should not be read as current. Development approvals, conditions, construction programs and litigation all change, frequently and without notice, and this article is a snapshot at November 2026 rather than a planning certificate. Anyone relying on a project in a purchase decision should obtain the current status from the consent authority and take advice from their own solicitor or planning consultant. The stage probabilities in section 04 are Alan Weiss’s personal judgement, not statistics. Includes Alan Weiss’s personal views. General information only; not financial, legal or planning advice.Ten projects I called jaw-dropping in 2023. Here is what actually got built.
Same ten projects, three years on. Filter by where each one actually is.
The cycleway is the clearest lesson in the whole list. Half of it is open. Half of it is in court.
The Kamay wharves opened in February 2025. There is still no ferry.
Two wharves, open to the public
The ferry service is a separate approval stage
“Approved” and “operating” are different words
Every project is at a stage. The stage tells you almost everything.
The list that matters now is mostly not the list from 2023.
Edgecliff and Woollahra
Woollahra station
160 Oxford Street, Paddington
209–215 Coogee Bay Road
Buying near something that has been announced? Let’s find out what stage it is actually at.
35+ years in Sydney’s Eastern Suburbs
Development watch · November 2026
1,360
Days between the Oxford Street cycleway first being proposed in November 2021 and the first stage opening on 25 July 2025. The second stage, the one through Paddington, is still not built and is now subject to legal action.
01 · The status board
The big one that came after
What the density rules now allow
02 · One project, five years
Oxford Street cycleway, 2021 to now
3 November 2021
First proposed as a permanent cycleway
October 2023 to March 2024
Construction slips twice
25 July 2025
Stage one opens, 1,360 days after it was proposed
5 August 2025
A petition to abandon stage two
2026
Legal action, and another extension
Still ahead
Stage two, unbuilt
03 · Built, and not finished
What was delivered
Feb 2025
What was not
Stage two
The lesson
Read the stage
04 · How to read an announcement
None of those are odds in any statistical sense and I would not pretend otherwise. They are how I weigh an announcement after thirty-five years of watching them, and they are deliberately more pessimistic than the press release. The useful discipline is simply this: before you pay a premium for a project, find out which stage it is at, and ask what the next gate is and who controls it.
05 · What has appeared since
State-led rezoning
New heavy rail
Approved September 2026
Refused September 2026
Before you buy near any of them
What the market looks like now
Weiss Real Estate · My read
I wrote that article in a voice that was not mine, and the voice was the problem, not the facts.
Buying near a project
Selling near one
Alan Weiss
Principal, Weiss Real Estate
Sources