Eastern Suburbs Projects 2026: What Got Built

–>

Development watch · November 2026

Ten projects I called jaw-dropping in 2023. Here is what actually got built.

That article listed ten developments coming to the Eastern Suburbs and described all of them as exciting. Every one was real and every description was accurate. What it did not do, and what any piece about infrastructure has to do if it is going to be useful, is tell you how likely each one was to happen and when. Three years later one of them is open and does not yet do what it promised, one is in the Land and Environment Court, several are approved and not started, and a few I simply cannot confirm either way. If you are buying near a project, that distinction is the only thing that matters.

1,360
Days between the Oxford Street cycleway first being proposed in November 2021 and the first stage opening on 25 July 2025. The second stage, the one through Paddington, is still not built and is now subject to legal action.

01 · The status board

Same ten projects, three years on. Filter by where each one actually is.

Where I have been able to confirm the current status from a primary source, I have. Where I have not, I say so rather than repeating the 2023 description as though it were current. That honesty is the point of the exercise.




The big one that came after

9,400 homes, 34 storeys and a new station: the Edgecliff–Woollahra rezoning.

What the density rules now allow

Precinct by precinct across the East: the LMR reforms.

02 · One project, five years

The cycleway is the clearest lesson in the whole list. Half of it is open. Half of it is in court.

I described it in one breezy sentence as ready to take us on a thrilling ride, with a note that it had seen some debate. Here is what “some debate” turned into.

Oxford Street cycleway, 2021 to now
3 November 2021
First proposed as a permanent cycleway

Identified as a high-priority missing link in the Eastern Harbour City strategic cycleway corridor between Bondi Junction and the CBD. The Bondi Junction cycleway opened in March 2023 and the Centennial Park cycleway back in 2014.

October 2023 to March 2024
Construction slips twice

Scheduled to start in October 2023, delayed to March 2024, with completion expected by the end of 2024.

25 July 2025
Stage one opens, 1,360 days after it was proposed

The Oxford Street West and Liverpool Street cycleway, connecting the CBD to Taylor Square, delivered by the City of Sydney. More than 2,000 riders a day already used the corridor, which was a recognised crash hot spot.

5 August 2025
A petition to abandon stage two

Lodged by the local member and signed by more than 500 people, calling for the 1.8 kilometre eastern section from Taylor Square to Centennial Park to be dropped. The Transport Minister formally rejected it.

2026
Legal action, and another extension

Two Paddington residents launched proceedings against the state government and the City of Sydney, alleging the project breaches human rights laws by discriminating against elderly people and those with a disability. Woollahra Council does not support the eastern section. The Moore Park Road pop-up cycleway, meant to be removed by 31 May 2026 or when Oxford Street East became operational, has been extended to 31 December 2026.

Still ahead
Stage two, unbuilt

Five years after the proposal, the section that would actually connect the Eastern Suburbs to the city is not under construction.

Sources: Transport for NSW; City of Sydney; Bicycle NSW; the Paddington Society; media reporting. Positions and timelines in a contested project change frequently.

03 · Built, and not finished

The Kamay wharves opened in February 2025. There is still no ferry.

This is the one I would most want a buyer to understand, because it is the pattern that catches people out. The infrastructure was delivered on schedule and to specification. The service it was built for is a separate stage that has not started.

What was delivered
Feb 2025

Two wharves, open to the public

The $49.3 million project replaced wharves at La Perouse and Kurnell as part of the Kamay Botany Bay National Park master plan, and opened for public use on 27 February 2025. They are roughly 230 metres at La Perouse and 250 at Kurnell, built for drop-off and pick-up berthing, fishing and gathering, with a seagrass restoration zone where anchoring is not permitted.

What was not
Stage two

The ferry service is a separate approval stage

Transport for NSW describes stage one as wharf operation and stage two as a potential future ferry connection, with conditions of approval to be met at each stage. As at the middle of 2026 the project page still refers to future ferry connections. A ferry ran between Kurnell and La Perouse from the 1890s until storms destroyed the wharves in 1974.

The lesson
Read the stage

“Approved” and “operating” are different words

If you bought in La Perouse or Phillip Bay on the strength of a twenty-minute ferry link replacing a ninety-minute drive, you own a very good wharf. The link itself requires an operator, a business case and a second set of conditions. None of that was secret. It was in the project documents the whole time, and none of it was in my article.

04 · How to read an announcement

Every project is at a stage. The stage tells you almost everything.

This is the tool I wish I had included in 2023. When an agent or a council or a developer tells you something is coming, the only useful question is which stage it is at, because each stage carries a very different probability and a very different timeframe. Pick one.






None of those are odds in any statistical sense and I would not pretend otherwise. They are how I weigh an announcement after thirty-five years of watching them, and they are deliberately more pessimistic than the press release. The useful discipline is simply this: before you pay a premium for a project, find out which stage it is at, and ask what the next gate is and who controls it.

05 · What has appeared since

The list that matters now is mostly not the list from 2023.

Three years is long enough for the pipeline to turn over. The projects most likely to affect Eastern Suburbs values today were not in that article because most of them did not exist yet.

State-led rezoning

Edgecliff and Woollahra

Up to 9,400 homes across 168 hectares, heights to 34 storeys at Edgecliff and 32 at the proposed Woollahra station. Exhibition closed 30 October 2026, outcome expected 2027. Far larger in consequence than anything on the 2023 list.

New heavy rail

Woollahra station

Construction slated to begin in 2027 for a 2029 opening, about eight minutes to the CBD. Sydney’s first new heavy rail station in more than a decade, and the single most durable change in this whole pipeline.

Approved September 2026

160 Oxford Street, Paddington

A state significant mixed-use development with infill affordable housing, determined on 24 September 2026 despite extensive community objection, with roughly 83 excavated parking spaces. A second proposal at Oxford and Verona Street is in assessment.

Refused September 2026

209–215 Coogee Bay Road

A five to six storey shop-top housing proposal with 13 apartments refused on 10 September 2026 over amenity, flooding, traffic, setbacks and desired future character. Coogee remains one of the harder approval environments in the East.

Before you buy near any of them

Contract, planning certificate, title and strata, in the order they matter: due diligence in NSW.

What the market looks like now

Clearance at 52.8% and values 10.1% below the February peak: downturns compared.

Weiss Real Estate · My read
I wrote that article in a voice that was not mine, and the voice was the problem, not the facts.

Reading it back is uncomfortable. Jaw-dropping, hold onto your hats, exciting times ahead my friends. Every project in it was real and correctly described, and the piece was still close to useless, because enthusiasm is not information. A person reading that article was probably trying to work out whether to pay more for a flat near one of those projects. Nothing in it helped them do that. The last four paragraphs were generic agent copy about being your guiding light, which is the part I would delete first.

What I would write instead is on this page. Of the ten, the wharves at Kamay are open and the ferry they were built for has not started. The Oxford Street cycleway took 1,360 days to deliver its first half and the second half is being litigated. The Coogee Bay Hotel was approved three years ago under a deferred commencement consent and the architects still list it as ongoing. Several of the rest I genuinely cannot confirm, and I would rather tell you that than repeat a 2023 sentence with a 2026 date on it.

The practical rule I have arrived at is simple and it has cost clients real money when they ignored it. Do not pay today for infrastructure that has not been built. If a station, a cycleway, a ferry or a shopping centre upgrade is in the price, you are funding someone else’s optionality. Buy the property for what it is now, on the street as it is now, and treat the project as upside you did not pay for. In the Eastern Suburbs over three decades that approach has never once left me explaining to a client why the thing on the brochure is still a vacant lot.

Buying near a project

Someone on your side of the table who will check the stage before you bid: my buying service.

Selling near one

How to price in genuine upside without promising what has not been approved: my selling service.

Buying near something that has been announced? Let’s find out what stage it is actually at.

Which approvals exist, which conditions are outstanding, who controls the next gate, and whether any of it should be in what you pay. Thirty-five years of watching Eastern Suburbs projects arrive late or not at all.

Alan Weiss
Principal, Weiss Real Estate
35+ years in Sydney’s Eastern Suburbs

Sources
  1. Transport for NSW, Kamay Wharves project page (reviewed 22 June 2026) and community update February 2025: the wharves at La Perouse and Kurnell were completed and opened for public use, with the project staged as wharf operation (stage one) and a potential future ferry connection (stage two); a marine biodiversity offset strategy runs as a ten-year approval requirement to 2033. Planning approval SSI-10049 was granted in July 2020. Reported project value $49.3 million, with wharves of approximately 230 metres at La Perouse and 250 metres at Kurnell. A ferry operated between Kurnell and La Perouse from the 1890s until storms damaged the wharves in 1974.
  2. City of Sydney and media reporting, 25 July 2025: the Oxford Street West and Liverpool Street cycleway opened, connecting the CBD to Taylor Square, 1,360 days after first being proposed on 3 November 2021; construction had been scheduled for October 2023, delayed to March 2024, with completion originally expected by the end of 2024.
  3. Bicycle NSW and the Paddington Society, 2025–26: the Oxford Street East cycleway from Taylor Square to Paddington Gates remains proposed, to be delivered by Transport for NSW on the southern side; more than 2,000 riders a day use the corridor and it is a recognised crash hot spot; a petition lodged on 5 August 2025 with more than 500 signatures seeking to discontinue the 1.8 kilometre eastern section was formally rejected by the Minister for Transport; Woollahra Council does not support the eastern section; two Paddington residents have commenced legal action against the state government and the City of Sydney alleging the project discriminates against elderly people and those with a disability; the Moore Park Road pop-up cycleway retention has been extended from 31 May 2026 to 31 December 2026. The Bondi Junction cycleway opened in March 2023 and the Centennial Park cycleway in 2014.
  4. Sydney Eastern City Planning Panel and reporting, 2023: the Coogee Bay Hotel redevelopment was granted a deferred commencement consent pending a noise masterplan, with a capital investment value reported at $94 million and works valued at $111 million; the approval covers refurbishment to 18 hotel rooms, a new three-storey building with 13 further rooms for 31 in total, five to six storey shop-top housing of 58 dwellings, 11 retail premises, an internal laneway eat-street from Coogee Bay Road, basement parking for 158 cars, subdivision and landscaping. Fender Katsalidis lists the project as ongoing, with a site of about 8,500 square metres and gross floor area of 30,342 square metres.
  5. Randwick City Council, 2026: a five to six storey shop-top housing proposal at 209–215 Coogee Bay Road with 13 apartments was refused on 10 September 2026 over amenity, flooding, traffic, parking, landscaping, waste, setbacks and desired future character; Council endorsed an additional $1.4 million for the Coogee Surf Life Saving Club ground floor refurbishment on 25 August 2026, including about $990,000 in grant funding.
  6. City Hub, 2023: Meriton’s Little Bay proposal was rejected for a third time in four years by the Department of Planning, with the Mayor and the Save Little Bay community group calling for Meriton to build to the existing approved master plan.
  7. NSW Planning Portal: 160 Oxford Street, Paddington (SSD-97528708), mixed use with infill affordable housing, approved with a determination date of 24 September 2026; a further proposal at Oxford and Verona Street (SSD-87245208) is in assessment. NSW Department of Planning, Housing and Infrastructure: Edgecliff–Woollahra Precinct state-led rezoning exhibited 8 September to 30 October 2026 with an outcome expected in 2027; Woollahra station construction slated to begin in 2027 for a 2029 opening.
  8. Alan Weiss, “Sydney’s eastern suburbs are about to undergo some jaw-dropping transformations!” (the original article this updates), and Weiss Real Estate campaign records, Eastern Suburbs.

Several projects from the original article could not be confirmed from a primary source and are marked unconfirmed rather than restated; their 2023 descriptions should not be read as current. Development approvals, conditions, construction programs and litigation all change, frequently and without notice, and this article is a snapshot at November 2026 rather than a planning certificate. Anyone relying on a project in a purchase decision should obtain the current status from the consent authority and take advice from their own solicitor or planning consultant. The stage probabilities in section 04 are Alan Weiss’s personal judgement, not statistics. Includes Alan Weiss’s personal views. General information only; not financial, legal or planning advice.